Duba Green Power Plant Civil & Electrical Works

Our diverse portfolio represents decades of construction experience backed by a passion for quality, outstanding client service and the latest industry technologies.

Duba Green Power Plant Civil & Electrical Works

Clients

Saudi Electricity Company

Main Contractor

SSEM

Region

Tabuk, Saudi Arabia

City

Duba

About Project

The Duba Green Power Plant project was undertaken for Saudi Electricity Company, with Saudi Services for Electro Mechanic Works Co. (SSEM) acting as main contractor. Alamaat Specialised Contracting delivered the assigned civil construction, reinforced concrete works, electrical cable installation and external site works under SSEM.

Activities extended from excavation and concrete foundations to plant structures, underground cable infrastructure, power cable pulling and external works. The resulting work package supported installation of the plant’s electrical and mechanical equipment by the main contractor.

Project Requirements

Power plant construction requires foundations to match equipment interfaces and electrical cable routes to be coordinated with civil works. SSEM needed concrete structures built to the specified dimensions and an orderly cable installation sequence without disrupting related construction activities.

Project Highlights

Complete reinforced concrete structures, from foundations to slabs
Walls and slabs built to engineering specifications
Duct banks and manholes for the underground cable network
Electrical cable pulling and installation
Complete external works around the plant
Work completed as subcontractor to SSEM

Work Scope & Execution

Foundations. The team carried out excavation, formwork, steel reinforcement and concrete pouring for the plant foundations, following the approved drawings and quality procedures.

Concrete structures. The team built all concrete structures required by the project, including walls and slabs, with controlled curing and inspection at each stage.

Duct banks and manholes. The team constructed the concrete duct banks and manholes that carry the plant’s underground electrical cabling, laid out for protection and easy access for future maintenance.

Cable pulling and installation. Our teams pulled and installed the electrical cables through the duct banks and manholes, handling and routing them carefully to protect insulation and keep the work orderly and safe.

External works. We also completed the external works for the site, including grading and backfilling, drainage, roads and paved areas, and other surface works, leaving the plant surroundings safe, well drained and ready for operation.

Coordination. We worked alongside SSEM’s engineers throughout, aligning our civil and electrical activities with the main contractor’s programme and the client’s safety standards.

Planning a similar project? Share your drawings and scope with our team to discuss construction and specialist contracting requirements.

CONTACT US

Start Your Next Project with Confidence

Partner with a trusted contractor delivering reliable construction and infrastructure solutions across Saudi Arabia.

Quick Enquiry

Call Me Back

Download Brochure

x

Quick Enquiry

Send us a message and we will reply you within 3 hours by email.

    x

    Call Me Back

    Send us a message and we will reply you within 3 hours by email.

      x

      Send Email Us

      Send us a message and we will reply you within 3 hours by email.