Clients

Saudi Electricity Company

Sector

Energy Infrastructure

City

Tabuk Province, Saudi Arabia

Scope

Transmission Structure Construction

Project Overview

The Tabuk 380kV BSP project comprises high-voltage 380kV, 230kV and 110kV yards alongside a control building. Working under Azzam Trading & Contracting Co. Ltd., Alamaat Specialised Contracting was responsible for specified civil construction, external site works and MEP installation.

The subcontract combined reinforced concrete and other civil works within the substation yards, construction of the control building, external infrastructure and installation of the building’s mechanical, electrical and plumbing services.

Project Requirements

Construction within a high-voltage substation requires accurate equipment foundations, properly organized yards and a control building suitable for sensitive electrical systems. Azzam needed the civil works, external infrastructure and building services delivered to the approved requirements within the project schedule.

Project Highlights

Civil works for the 380kV, 230kV and 110kV yards
Construction of the control building
Complete external works as part of our main scope
MEP installation works
Completed as subcontractor to Azzam Trading & Contracting

Work Scope & Execution

Yard civil works. The team carried out excavation, formwork, reinforcement and concrete works for the 380kV, 230kV and 110kV yards, including the equipment foundations and supporting structures, built against the approved drawings and tolerances.

Control building. The team constructed the control building structure and its civil finishes, ready to receive the substation’s control and protection equipment.

External works. External works formed part of our main scope: site grading, drainage, roads and access areas, and surface finishing around the yards and building.

MEP installation. The site team installed the mechanical, electrical and plumbing systems of the project, in line with the supplied materials and approved drawings, then tested them for handover.

Coordination. Site coordination involved Azzam’s engineers and followed the client’s safety and quality procedures on every activity.

Planning a similar project? Share your drawings and scope with our team to discuss construction and specialist contracting requirements.

CONTACT US

Start Your Next Project with Confidence

Partner with a trusted contractor delivering reliable construction and infrastructure solutions across Saudi Arabia.

x

Quick Enquiry

Send us a message and we will reply you within 3 hours by email.

    x

    Call Me Back

    Send us a message and we will reply you within 3 hours by email.

      x

      Send Email Us

      Send us a message and we will reply you within 3 hours by email.